4. Programme, sequencing and access
Carpentry is a sequence trade. Joists sit between the bricklayer and everything else, and a slipped joist date pushes the roof, the first fix and the plasterer behind it. So the enquiry should state not only the dates but the shape of the work: how many plots are available at once, in what order, and what has to be finished before we can start each one.
Three questions decide whether a programme is realistic. Will the plots be available in a continuous run, or in ones and twos with gaps between them? Is the building watertight before second fix, because doors, kitchens and MDF trim in a damp building will move and you will pay for it twice? And who controls access to the areas we need, particularly in occupied buildings and phased handovers?
A subcontractor that employs its carpenters can flex to that. AJB Group runs external and internal teams in parallel, so a roof gang can be working on one phase while a first fix gang works another. Capacity is why plot output on the Long Sutton estate reached six attic roofs in a day, and why a 300 home development can have completed houses standing next to plots still at joist stage without the package stalling.
5. Stores, deliveries and protection
Every moisture sensitive item in a carpentry package is a claim waiting to happen if it is stored badly. Doors, kitchens, MDF trim, staircases and sheet materials all need to be dry, flat and off the ground, in a building that has stopped drying out. Trusses need to be stored upright and supported, not stacked flat in the mud, and they are heavy, awkward and easy to damage.
State in the enquiry where materials will be stored, whether that store is lockable, whether there is a delivery route for an artic, and when the building will be watertight. If those answers are poor, tell the tenderers, because pricing around a bad store is possible and discovering it in week three is not.
6. The commercial mechanics
- Measurement basis. Per plot, per unit or per measured item. Agree it before the first valuation, so a part complete plot is arithmetic rather than opinion.
- Variations priced before they happen. In writing, against the package rates where they exist. A verbal instruction priced months later at valuation is how good relationships end.
- Provisional sums and dayworks. Say what is provisional and what the daywork rates are, rather than leaving both to be argued.
- Valuation dates, payment terms and retention. Standard, but state them, along with the notice regime.
- Design responsibility. Say clearly whether any element carries subcontractor design, for example a posi-joist layout or a staircase. If it does, that changes the insurance position, so say it at enquiry rather than in the order.
- Defects and snagging. How many returns are included, and what triggers them.
7. Compliance and handover information
Ask for the pre-qualification pack at enquiry stage: project specific risk assessments and method statements rather than a generic set from another job, evidence of accreditation and competence, current insurance, plant and trade certification, and named supervision. AJB Group is CHAS accredited and SMSTS certified with a retained external health and safety consultant, and issues project specific RAMS before mobilisation. Full detail on the accreditations page.
Then decide at tender stage what you need at handover, because collecting it retrospectively is painful. On any package containing fire doors that means the door schedule, the certification references and the installation records, which the responsible person needs in order to discharge their own duties. Ask for it in the enquiry and it gets recorded as the work is done rather than reconstructed from memory in the last week.